Crowd at school taps before we added the 3" pipes. |
Crowd waiting at the ten taps at the school. |
2. Have the water close to home so you do not spend as much time fetching.
3. Have good quality of water.
On Thurday and Friday May 3 and 4 we went back to
Banjiram to bring them the pipes and parts to improve the performance of the
distribution system. The modeling for the re-design of the system starts to work with adding 270 meters
of 2-½ inch pipe. It works better with 3 inch. Due to supply and demand currently the 3 inch pipe is cheaper than the 2-½ . I had been told that the buried pipes
going out to the remote tap stands were 1-½ inch pipes. We only purchased
fittings that would connect the 3 inch to the 1-½ inch. It took most of the
morning to get the right pipes and the right lengths onto a truck to transport
it out to Banjiram. The 6 meter long pipes that shop was selling were actually 4.92 meters long. We had to measure the pipes and recalculate how much we needed. We
now needed 78 of the 4.92 meter pipe and they were still cheaper than the 2-½ inch pipe .
They did not have 1-½ inch tees so they sent out some boys
to their other shop to get them. They finally, came back and tossed them in the
bag of parts. I should have looked at them. They were 2 inch tees. It really
did not matter because the pipe in the ground was actually 1-¼ inch. It also took a long time to get the 78 pipes from his other warehouse and loaded onto a truck. We made sure the driver knew where to go and we headed out at a little after 11. Our trucks had been parked facing each other. He went one way and we headed in the opposite. We had to get fuel and make a stop in Numan to deliver some paperwork to the Health Board Director. We did not know that the truck driver was headed to his house to get a second rack for his truck. He did not like the way the pipes were hanging on back of his truck with only one rack. The pipes showed up about two hours after we got to Banjiram. While we were waiting for him we had the people start digging a wider trench for the pipes and explained to the plumber what we were going to do. He was unconvinced that it would work, The pump in the borehole was only a 1-¼ inch pipe so he reasoned that it was too small to push water through a 3 inch pipe. I tried to explain to him. He just shook his head. He was being paid he will make the connections.
We off loaded the pipes by the tower and when the plumber was ready the men, women and kids all grabbed pipes and took them to the trench. On
Thursday we connected assembled and buried all the 3 inch pieces and decided
on what parts we needed to finish the work on Friday. We also looked at the existing
leaks in the system and made a list of repair parts. We rushed back to Yola and
started searching for the parts just before sundown. The shops were trying to close and get home before dark. Most of what we needed were found at the third shop we tried.
Friday morning, Yakubu could not come with us so I was the driver. Adams and I located the final parts and were on the road to Banjiram by 9. We arrived and
called the plumber to drive down from Guyuk about 15 kilometers further up the
road. Everything went smoothly until we started trying to repair the 20 year
old valves and coupling that were leaking. I have to give the plumber credit. He was able to hammer and force these old rusted fittings loose. The leaks were because of the
misalignment of the pipes as much as the age of the parts. Some of the old buried pipes had to be moved a few inches. We had hoped to be
finished by noon so we could pump some water during peak solar power. We were
finally able to get the leaks down to a few minor drips at just after 2 pm.
![]() |
Everyone stepped back to let me get a picture of the water. |
Five hours of pumping had been missed for the day. The sun was past it peak and there was no water in the tank. Usually the tank is half full when the system is opened. At
2:30 we turned on the water to the distribution system. It now had to fill 260
meters of 3 inch pipes. The North Pipe stand that used to have only 2 of the 8
taps working had good flow at all 8 taps after taking 30 minutes to fill the
lines. The South tap stand that usually had 5 taps flowing only had two. We had
the women at the North Tap Stand singing and dancing and the women at the South
Tap Stand looking for a rope to hang me with. Finally, Adams checked a valve
that the operator had told us was wide open and found it was closed. A few
minutes after he opened it the South Tap Stand had 4 of the 8 working. It was
not late in the day and past the peak solar time. Adams explained to the
women that the pump had been off all day as we worked on the system and there was not water in the tank. He told them it will be better tomorrow. (When we would be safely back
in Yola.)
The next day as I sat in the LCCN Cathedral in Yola at a wedding ceremony for 5 couples a lady came and sat down next to me. She said "I am from Banjiram. You are a brother of Banjiram." She must live near the North Tap Stand.
The next day as I sat in the LCCN Cathedral in Yola at a wedding ceremony for 5 couples a lady came and sat down next to me. She said "I am from Banjiram. You are a brother of Banjiram." She must live near the North Tap Stand.
Line for water at the artesian flow while we worked. |
No comments:
Post a Comment